Jane is an experienced project manager. As part of the Collect Requirements phase, she decides to use a group creativity technique. This technique is expected to enhance brainstorming with a voting process, and can be used to rank the most useful ideas for further brainstorming or prioritization. Which of the following will she likely use?
A. Normal group technique
B. Minimal group technique
C. Unanimous group technique
D. Nominal group technique