PMP Exam Set D – Q39

A project to design and build a new aircraft is cancelled after the project has been underway for some time. What process is invoked to document what work was done, and to what extent it was completed?

A. Manage Scope
B. Close Scope
C. Perform Quality Control
D. Close Project or Phase

D. Close Project or Phase