PMP Exam Set D – Q45

You are a PMP who is nearing the end of an important project. You have spent considerable energy on this project nurturing a cooperative relationship between your organization and the customer. What is the customer’s MOST important role in bringing the project to a close?

A. The customer is delivered the last shipment of the product, service, or result
B. The customer acknowledges the delivery of the last shipment of the product, service, or result
C. The customer provides formal acceptance of the product, service, or result
D. The customer makes a final payment for the work completed on the project

C. The customer provides formal acceptance of the product, service, or result