PMP Exam Set D – Q78

It was found that there were a large number of hidden requirements to be uncovered in the Collect Requirements phase. Which of the following tools should a project manager use to identify them?

A. Participant observer
B. Questionnaires
C. Surveys
D. Interviewing

A. Participant observer