In the procurement process, the seller may be viewed initially as a bidder, then as the selected source and then as the contracted supplier. The seller will typically manage the work as a project. In such an instance, which of the following is not true?
A. The Buyer becomes the customer and is thus a key project stakeholder for the seller.
B. Terms and conditions of the contract become key inputs to many of the seller’s management processes. (ex: major deliverables, key milestones, cost objectives)
C. There need not be a contractual relationship between the buyer and the seller
D. The Seller’s project management team is concerned with all the processes of project management and not just Procurement management.