PMP Exam Set D – Q84 ( PMBOK 6th edition )

A project manager is planning out the availability of resources as part of the Acquire Resources process. He needs to acquire resources that report to a functional manager. What technique will he likely use to obtain these resources?

A. Pre-assignment
B. Authority
C. Negotiation
D. Coercion

C. Negotiation