You have been asked to fill in for another project manager while he is on vacation. During the next project status meeting, you ask for a risk report. The project team says they have never reported on that before, and are unsure if there is a master project risk log. What do you do?
A. Do nothing.
B. Develop a list of risks yourself, based on experiences you have had managing similar projects.
C. Ask the team to brainstorm the risks they think may impact the project.
D. Notify the project stakeholders.