PMP Exam Set E – Q27

A number of deliverables were submitted to the buyer as part of a project. Where would the project manager find documentation on the requirements for formal deliverable acceptance and how non-conforming deliverables can be addressed?

A. In the SOW
B. In the lessons learned document
C. In the deliverable release note.
D. In the agreement

D. In the agreement