To control the schedule, a project manager is re-analyzing the project to predict project duration. This is done by analyzing the sequence of activities with the least amount of flexibility. What technique is being used?
A. Leads and lags
B. Work Breakdown Structure
C. Flowchart
D. Critical Path Method