PMP Exam Set E – Q4

For your weekly project status review meetings, you set some time aside on the agenda to review the risk register and review the project risks. You ensure that the response plans are still appropriate and add or delete risks as necessary. This is an example of?

A. Technical Performance Measurement
B. Trend Analysis
C. Risk Reassessment
D. Risk Audit

C. Risk Reassessment