PMP Exam Set E – Q42

________________ includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

A. Statement of Work
B. Project Schedule Management
C. Project Scope Management
D. Work breakdown structure

C. Project Scope Management