PMP Exam Set E – Q44

While managing a project, you decide to contract to an external enterprise. You enter into a contract where you pay the external enterprise a set amount (as defined by the contract), irrespective of the seller’s costs. What would best describe this type of contract?

A. FP-EPA
B. FFP
C. FPIF
D. CPFF

B. FFP