PMP Exam Set E – Q55

Which of the following statements is NOT true considering the management of risks in a project?

A. The affect of various risks on project scope, cost and quality is numerically analyzed in the perform quantitative risk analysis process
B. Positive risks are mitigated during the plan risk responses process.
C. Analytical techniques are used during the plan risk management process
D. The risk register is updated in all risk management processes except in plan risk management

B. Positive risks are mitigated during the plan risk responses process.