Emily is the project manager for a dam construction project. All project communications are recorded and documented for future reference. It has been decided that the project team will maintain last three months of project communication records at any given point in time. It has also been decided that the older communication records will be archived on a monthly basis. Where these records must be archived?
A. Change log
B. Organizational process assets
C. Enterprise environmental factors
D. Issue log