PMP Exam Set E – Q71

Andrew is the project manager of a project and is planning responses to a set of risks. As a direct response of implementing this risk response, he anticipates certain other risks to arise. These would be termed as:

A. Secondary risks
B. Primary risks
C. Planned risks
D. Workaround

A. Secondary risks