PMP Exam Set E – Q8

A project team is currently inspecting the recent project deliverables. The team is recording the number and the nature of defects found in these deliverables. The defect details list in this case is an example of?

A. Quality control checklist
B. Work performance data
C. Change request
D. Work performance information

B. Work performance data