PMP Exam Set E – Q89

During a key stakeholders update meeting, George’s project was challenged. The project is currently in the executing phase. One of the key stakeholders challenged that the project no longer makes any business sense to her. What must George do next?

A. Update the issue log and request the stakeholder to provide more details.
B. Request the project sponsor to intervene.
C. Prematurely terminate the project.
D. Redo the business case for the project.

A. Update the issue log and request the stakeholder to provide more details.