Peter has been assigned to build a new office facility for his organization. Peter finds out that there are a big number of key stakeholders that are neutral to the project. Peter’s stakeholder management strategy must focus on?

A. Reducing the number of project stakeholders.
B. Ensuring these neutral stakeholder remain neutral till the project closure.
C. Ensuring these neutral stakeholders do not convert to resistant stakeholders till the project closure.
D. Converting these neutral stakeholders to supportive stakeholders.

D. Converting these neutral stakeholders to supportive stakeholders.