While preparing a human resource plan, a project manager documented that one of the senior programmers in the team would make decisions on whether the quality of deliverables from the project met the project’s documented standards. Which of the following aspects of a human resource plan does this address?
A. Competency
B. Responsibility
C. Authority
D. Role