Emily has been assigned as the project manager of a project. After a detailed discussion with the project management team, she decides to come up with a quality management plan that is informal and broadly framed. What would your comment on this be?
A. This is incorrect. A quality management plan should be formal but broadly framed.
B. This is incorrect. A quality management plan should be formal and highly detailed.
C. This is fine. The style and detail of the quality management plan is determined by the requirements of the project.
D. This is incorrect. A quality management plan should be informal and highly detailed.