PMP Exam Set F – Q23

Peter is the project manager of a project that is halfway through the execution. Peter is currently looking at the schedule of work. He adjusts a few of the schedule milestones and imposes date constraints for some of the work packages. This relates to which of the following processes?

A. Control Quality
B. Develop Schedule
C. Control Scope
D. Control Schedule

D. Control Schedule