You are managing the communication requirements for your project. You find that certain general management skills come into play as part of managing stakeholder requirements and that there are different dimensions to communication that you have to plan for as the sender of information. Which of the following is not a dimension of communicating?

A. Vertical / Horizontal communication
B. Forward / backward communication
C. Formal / Informal communication
D. Internal / external communication

B. Forward / backward communication