PMP Exam Set F – Q41

Jane is managing a multi-million dollar shopping complex construction project. The buyer of the project is an external entity. After identifying all the key and major project stakeholders, Jane is now planning to carry out a comprehensive stakeholder analysis. Which of the following is not involved with the stakeholder analysis?

A. Identifying potential stakeholders
B. Identifying stakeholder relationships
C. Resolving stakeholder conflicts
D. Determining stakeholders’ interests and expectations

C. Resolving stakeholder conflicts