PMP Exam Set F – Q46

Jane works as a project manager for the National weather agency. She has been managing a project which was designed to find the impact of climate changes on Northern mountains. The initial study established two months delay for the testing equipment to reach mountains due to road construction. However, a recent assessment has shown a significant drop in the delay time because of rapid progress in construction. Which of the following steps should Jane take next to account for the change in the delay time?

A. Distribute the information
B. Conduct a stakeholder meeting
C. Create a new project plan
D. Update the risk register

D. Update the risk register