When are risk identification activities performed?
A. During the Perform Qualitative Risk Analysis process
B. During the Plan Risk Management process
C. During the Perform Quantitative Risk Analysis process
D. Ongoing throughout the project
When are risk identification activities performed?
A. During the Perform Qualitative Risk Analysis process
B. During the Plan Risk Management process
C. During the Perform Quantitative Risk Analysis process
D. Ongoing throughout the project