Which of the following is accurate regarding the Estimate Activity Resources process?
A. It produces project resource calendars as the output
B. It determines dependencies that may require a lead or lag to define the relationship
C. This process is coordinated independent of the Estimate Cost process
D. It involves determining what and how many resources will be used