Which of the following is accurate regarding Project Integration Management?
A. Project deliverables are not part of Integration Management
B. It involves the integration of process groups and not individual processes
C. The need for it becomes evident in situations where individual processes interact
D. It involves disregarding trade-offs and focuses on clearly articulating how accomplish all requirements by the deadline