PMP Exam Set F – Q8

A project team has recently computed the project’s current schedule and cost performance indices. They have also calculated the new estimate to complete and the TCPI based on the new estimate at completion. The project key stakeholders are not fully aware of the earned value management process. These measures in this case are an example of ?

A. Work performance data
B. Lessons learned
C. Work performance information
D. Learning curve for the stakeholders

A. Work performance data