As part of risk planning, some responses are designed for use only if certain events occur. A project manager of a multi-year project decided to trigger one such set of responses during the Monitor Risks process. Which of the following is likely to have triggered the responses?
A. Late receipt of status reports
B. A key employee going on vacation for three days.
C. Errors found in a deliverable document
D. Missing an intermediate milestone