PMP Exam Set F – Q98

The scope of work in a project could not be clearly defined. There was also a strong possibility that the scope would be altered during the course of the project. Which type of contract would suit this type of situation?

A. Fixed price with economic price adjustment contract
B. Fixed-price contract
C. Cost-reimbursable contract
D. Fixed price incentive contract

C. Cost-reimbursable contract