Which of the following is neither an input nor an output of the Direct and Manage Project Work process?
A. Approved change requests
B. Change requests
C. Approved deliverables
D. Deliverables
Which of the following is neither an input nor an output of the Direct and Manage Project Work process?
A. Approved change requests
B. Change requests
C. Approved deliverables
D. Deliverables