You are working as a project manager for MICTECH, an IT organization having a projectized organization structure. You have recently started managing a project that involves stakeholders from within and outside your organization. The stakeholders external to your organization are very critical as their interests are negatively affected by the project. You are making serious efforts to gather their expectations and influence levels early in the project to make sure that their voice is heard and proper communication needs can be planned in the future phases of the project. The outcome of your effort can be documented in:
A. The stakeholder management plan
B. The project scope document
C. The risk register
D. The stakeholder communication plan