You have just received notice that the organization you’ve been working for as a project manager has gone bankrupt. All employees have been given 72 hours notice of termination. What is the best course of action for the two projects you are managing?
A. Follow company directives.
B. Conduct a project closeout meeting.
C. Leave the office today.
D. Raise a claim for and on behalf of all the employees and contractors who were participating in the project