PMP Exam Set G – Q32

The sponsor of your facilities upgrade project has left the company to another organization. Few weeks later, you are reviewing the business case for the project and discover that there are several inconsistencies between what is stated in the business case and what is described in the project scope. Further research shows that the business case as a whole is based on inaccurate information. What do you do?

A. Notify your project stakeholders immediately.
B. Add this this to the risk log.
C. Update the requirements.
D. Call the sponsor for clarification.

A. Notify your project stakeholders immediately.