A manager asks you to evaluate four new projects that he has suggested for next year. You review the projects and notice that one is not really a project, but more an operational task. Which of these is not a project?
A. Change the product to enable increased consumer usage
B. Manage a set of people for the next year to deliver the desired productivity results
C. Respond to a customer request for different product packaging
D. Resolve a space constraint issue by building a new addition to the plant