A first-time project manager was assigned to a project that had a duration of 3 months. In order to gain a head start in the project, she took an older, completed project and incorporated all the tools, techniques and checklists from that project in their entirety into the current one. The older project had been completed in 14 months’ time and was very similar in nature. The most appropriate comment on this would be:
A. This is an excellent example of reuse of artifacts from prior projects.
B. This may be unnecessary. The project management team needs to decide what is appropriate for the project.
C. This is not the correct procedure. The project manager should always create processes and documents afresh for new projects.
D. This is not correct. The project manager is violating copyright and intellectual property rights of the organization’s prior customers.