Jane is the project manager for a healthcare facility construction project. She is currently holding a board briefing and updating the project’s current status to the board members. When Jane was presenting her project risks, the chairman suggested some preventive actions. What should Jane do first?

A. Jane should politely deny the request
B. Jane should write a change request
C. Jane should directly update the project management plan as the request has come from the Chairman
D. Jane should escalate the issue to the project sponsor

B. Jane should write a change request