There are a number of risks that have been identified in your project. The team has elected not to change the project plan to deal with the risk, but they have established a contingency reserve of money in the event some of these risks are triggered. This is an example of what type of risk mitigation technique?
A. Contingent Response Strategy
B. Active acceptance
C. Passive acceptance
D. Avoidance