PMP Exam Set E – Q95 ( PMBOK 6th edition )

You are an experienced project manager and have managed several data center migration projects. You are currently conducting training on the databases, spreadsheets and management plans you will be using during the lifecycle of the project. This training is a tool and technique in what process?

A. Manage Team
B. Acquire Resources
C. Develop Team
D. Control Quality

C. Develop Team

PMP Exam Set A – Q90

A fellow project manager is retiring and moving to the mountains, you will be taking over his project. Before he leaves he tells you the project is on schedule, but only because he has had to “put the hammer down” on his project team and push them relentlessly. Pushing the team to perform activities to accomplish project objectives is a part of:

A. Direct and Manage Project Work
B. Monitor and Control Project Work
C. Control Quality
D. Control Scope

A. Direct and Manage Project Work