PMP Exam Set D – Q8

A project is contracted as a Cost-Plus-Fixed-Fee (CPFF) type of contract. The targeted cost is US$ 200,000 with a fee of US$ 30,000. If the project comes in at US$ 170,000, what would be the cost of the total contract?

A. US$ 195,500
B. US$ 230,000
C. US$ 200,000
D. US$ 170,000

C. US$ 200,000