PMP Exam Set F – Q61

Which of the following is accurate regarding the Estimate Activity Resources process?

A. It produces project resource calendars as the output
B. It determines dependencies that may require a lead or lag to define the relationship
C. This process is coordinated independent of the Estimate Cost process
D. It involves determining what and how many resources will be used

D. It involves determining what and how many resources will be used