PMP Exam Set G – Q7 ( PMBOK 6th edition )

You have your project team members record the time they spend on different activities during the day such as: programming, electrical, HVAC, etc. This is an example of a tool and technique in what process?

A. Manage Communications
B. Direct and Manage Project Work
C. Monitor and Control Project Work
D. Manage Team

C. Monitor and Control Project Work

PMP Exam Set E – Q68 ( PMBOK 6th edition )

Which of the following is the process of communicating and working with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholder engagement?

A. Manage Stakeholder Engagement
B. Monitor Stakeholder Engagement
C. Manage Communications
D. Monitor Communications

A. Manage Stakeholder Engagement