PMP Exam Set G – Q7 ( PMBOK 6th edition )

You have your project team members record the time they spend on different activities during the day such as: programming, electrical, HVAC, etc. This is an example of a tool and technique in what process?

A. Manage Communications
B. Direct and Manage Project Work
C. Monitor and Control Project Work
D. Manage Team

C. Monitor and Control Project Work

PMP Exam Set A – Q90

A fellow project manager is retiring and moving to the mountains, you will be taking over his project. Before he leaves he tells you the project is on schedule, but only because he has had to “put the hammer down” on his project team and push them relentlessly. Pushing the team to perform activities to accomplish project objectives is a part of:

A. Direct and Manage Project Work
B. Monitor and Control Project Work
C. Control Quality
D. Control Scope

A. Direct and Manage Project Work