PMP Exam Set C – Q52

Set C Q52

What is the free float for Activity B?

A. 2 days
B. 3 days
C. 4 days
D. 5 days

A. 2 days
Tagged with 
free float Project Network Diagram
 

PMP Exam Set C – Q50

Set C Q50

What is the critical path for this project?

A. 11 days
B. 13 days
C. 14 days
D. 16 days

C. 14 days
Tagged with 
critical path method Project Network Diagram
 

PMP Exam Set B – Q2

What is the free float for Activity C?

A. 4 days
B. 5 days
C. 6 days
D. 7 days

C. 6 days
Tagged with 
free float Project Network Diagram
 

PMP Exam Set A – Q1


What is the free float for Activity C?

A. 3 days
B. 4 days
C. 5 days
D. 6 days

B. 4 days
Tagged with 
free float Project Network Diagram
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2023 Premium PMP Exam Questions
×Close