You are the Project Manager for the production of an exotic car. You have completed the Define Scope process for your project. Which of the following may be generated through this process?
A. Project scope statement, Project charter
B. Project scope statement, Updates to Requirements traceability matrix
C. WBS, Updates to Requirements traceability matrix
D. Project scope statement, WBS