Due to the unexpected release of a similar product from a competitor, the Widgets International executive team has stepped up the pressure on the product team to release the Widget product 3 months earlier. The project manager uses what technique to shorten the schedule but maintain the project scope?
A. Schedule compression
B. Rolling wave planning
C. Schedule network analysis
D. Schedule management planning