You are planning a storage device migration in a data center. During this phase of the project, who should be controlling the project?
A. Project Manager
B. SME’s
C. Sponsor
D. Management
You are planning a storage device migration in a data center. During this phase of the project, who should be controlling the project?
A. Project Manager
B. SME’s
C. Sponsor
D. Management
A project can be authorized by any of the following except:
A. The project manager
B. The PMO
C. The sponsor
D. The portfolio steering committee