PMP Exam Set E – Q53

You are working on a project where a negative risk has occurred. However, you have no contingency plan for this risk. You call a meeting and a solution is devised to change the workflow until a permanent solution can be implemented. This is an example of?

A. Work Item
B. Workaround
C. Work Package
D. Reserve plan

B. Workaround