PMP Exam Set A – Q39

A project manager estimated that a project would require 4375 person hours of effort. The project ended up using 6250 person hours of effort. The difference between these two figures is called a:

A. Variance
B. Control Limit
C. Threshold
D. Standard Deviation

A. Variance