A point in time that a project or project phase is authorized to its completion is called:
A. Project scope
B. Control limit
C. Project threshold
D. Project boundary
A point in time that a project or project phase is authorized to its completion is called:
A. Project scope
B. Control limit
C. Project threshold
D. Project boundary
A project manager estimated that a project would require 4375 person hours of effort. The project ended up using 6250 person hours of effort. The difference between these two figures is called a:
A. Variance
B. Control Limit
C. Threshold
D. Standard Deviation